Qt Creator Releases: Difference between revisions

From Qt Wiki
Jump to navigation Jump to search
No edit summary
No edit summary
 
(105 intermediate revisions by 4 users not shown)
Line 1: Line 1:
[[Category:Tools::QtCreator]]
[[Category:Tools::QtCreator]]
===Upcoming Releases===
Tentative dates:
Qt Creator 14
* Feature freeze wk22 (~May 30 2024)
* Beta release wk24 (~Jun 13 2024)
* String freeze wk26 (~Jun 27 26 2024)
* RC release wk28 (~Jul 11 2024)
* Final release wk30 (~Jul 25 2024)
Qt Creator 15
* Feature freeze wk40 (~Oct 3 2024)
* Beta release wk42 (~Oct 17 2024)
* String freeze wk44 (~Oct 31 2024)
* RC release wk46 (~Nov 14 2024)
* Final release wk48 (~Nov 28 2024)
The mentioned dates are typically Thursdays of the weeks, packages are meant to be ready by Tuesday. Actual release then typically happens on Wednesday or Thursday.
A collection of older release plans is found at [[Old Qt Creator Releases]].


===Qt Creator Release Cycle===
===Qt Creator Release Cycle===


We aim for 3 Qt Creator minor releases each year. Each minor release goes through the following stages before the final release date:
We aim for 3 Qt Creator major releases each year. Each release goes through the following stages before the final release date:


* T-8 Weeks: Feature freeze
* T-8 Weeks: Feature freeze
Line 13: Line 37:
These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.
These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.


Patch releases can happen after the final release, mostly with the scope of fixing brown paper bag and high priority issues (see also the [[Submit-Policies|Qt Creator Submit Policies]] ''[qt.io]''). We do not maintain multiple Qt Creator minor releases in parallel, usually there is no patch release after the beta of the next minor release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.
Patch releases can happen after the final major release, mostly with the scope of fixing embarrassing bugs and high priority issues (see also the [[Submit-Policies|Qt Creator Submit Policies]] ''[qt.io]''). We do not maintain multiple Qt Creator major releases in parallel, usually there is no patch release after the beta of the next release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.
 
The schedule for the next minor is typically set around release time, starting with a period about two months which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)
 
===Upcoming Releases===
 
Tentative dates:
 
Qt Creator 4.2:


* Feature freeze w42 (~Oct 11 2016)
The time after a final (.0) release starts with a period of about two months (52 weeks / 3 releases - 8 weeks from feature freeze to final = 9 1/3 weeks) which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)
* Beta release w44 (~Oct 25 2016)
* String freeze w46 (~Nov 8 2016)
* Release candidate w49 (~Nov 30 2016)
* Final release w51 (~Dec 13 2016)
 
The mentioned dates are typically Tuesdays of the weeks, packages are meant to be ready by then. Actual release typically happens on Wednesday or Thursday.
 
A collection of older release plans is found at [[Old Qt Creator Releases]].

Latest revision as of 10:00, 18 April 2024


Upcoming Releases

Tentative dates:

Qt Creator 14

  • Feature freeze wk22 (~May 30 2024)
  • Beta release wk24 (~Jun 13 2024)
  • String freeze wk26 (~Jun 27 26 2024)
  • RC release wk28 (~Jul 11 2024)
  • Final release wk30 (~Jul 25 2024)

Qt Creator 15

  • Feature freeze wk40 (~Oct 3 2024)
  • Beta release wk42 (~Oct 17 2024)
  • String freeze wk44 (~Oct 31 2024)
  • RC release wk46 (~Nov 14 2024)
  • Final release wk48 (~Nov 28 2024)

The mentioned dates are typically Thursdays of the weeks, packages are meant to be ready by Tuesday. Actual release then typically happens on Wednesday or Thursday.

A collection of older release plans is found at Old Qt Creator Releases.

Qt Creator Release Cycle

We aim for 3 Qt Creator major releases each year. Each release goes through the following stages before the final release date:

  • T-8 Weeks: Feature freeze
  • T-6 Weeks: Beta release + soft string freeze
  • T-4 Weeks: String freeze
  • T-2 Weeks: Release candidate
  • T-0 Weeks: Final release

These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.

Patch releases can happen after the final major release, mostly with the scope of fixing embarrassing bugs and high priority issues (see also the Qt Creator Submit Policies [qt.io]). We do not maintain multiple Qt Creator major releases in parallel, usually there is no patch release after the beta of the next release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.

The time after a final (.0) release starts with a period of about two months (52 weeks / 3 releases - 8 weeks from feature freeze to final = 9 1/3 weeks) which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)