Line 19: | Line 19: | ||
|- | |- | ||
| [http://wiki.qt.io/Qt5_feature_freeze Feature freeze] | | [http://wiki.qt.io/Qt5_feature_freeze Feature freeze] | ||
| T- | | T-17 weeks | ||
|- | |- | ||
| Alpha release | | Alpha release | ||
| T- | | T-13 weeks | ||
|- | |- | ||
| Beta release | | Beta release | ||
| T- | | T-8 weeks | ||
|- | |- | ||
|Soft string freeze | |Soft string freeze | ||
Line 31: | Line 31: | ||
|- | |- | ||
| Hard string freeze | | Hard string freeze | ||
| T- | | T-5 weeks | ||
|- | |- | ||
| Release candidate | | Release candidate |
Revision as of 11:19, 18 March 2016
This article may require cleanup to meet the Qt Wiki's quality standards. Reason: Auto-imported from ExpressionEngine. Please improve this article if you can. Remove the {{cleanup}} tag and add this page to Updated pages list after it's clean. |
Qt 5 releasing gearbox
We are targeting to release new minor Qt release twice/year and some patch releases between those minor ones. Target is to release minor releases on April and October. Patch releases are done pretty much need bases: Those can be done immediately when some brown paper bag issue is found & fixed (e.g. security fix) or when there is enough critical issues fixed for next Patch release.
Most of releasing related issues are decided in virtual release team meetings. Meetings are led by release manager and everyone can join to those meetings by informing willingness to release manager. Meetings are held in irc, #qt-releases channel. To get invitation to these meetings please sent request to the release manager.
Qt 5 release phases
Patch release doesn't have official release phases; It is released when needed and when quality is good enough.
Minor releases are going through following phases:
Phase | Timing |
---|---|
Feature freeze | T-17 weeks |
Alpha release | T-13 weeks |
Beta release | T-8 weeks |
Soft string freeze | T-6 weeks |
Hard string freeze | T-5 weeks |
Release candidate | T-2 weeks |
Final release | T |
Timings are more or less suggestive and will be fine-tuned for each release to take care of holiday seasons etc.
Qt releases
In the table below is high level schedule. Detailed schedule & patch releases can be found from subpages, links in the each release.
Qt release | Planned schedule | Actual schedule |
---|---|---|
Qt-5.1-release | May 2013 | July 2013 |
Qt-5.2-release | Nov 2013 | Dec 2013 |
Qt-5.3-release | Apr 2014 | May 2014 |
Qt-5.4-release | Oct 2014 | Dec 2014 |
Qt-5.5-release | Apr 2015 | July 2015 |
Qt-5.6-release | Dec 2015 | March 2016 |
Qt-5.7-release | Apr 2016 | <tbs> |
Qt-5.8-release | Oct 2016 | <tbs> |
Branches & Qt versions
There is few different development branches in Qt 5: Development branch & feature branches (like 5.4, 5.3)
Development branch has content targeted to next minor release (Qt 5.x). After feature freeze of Qt 5.x code is branched from development branch to 5.x and work for that minor release continues in that new branch. Development branch is again for new minor release Qt 5.(x+1).
Feature branches (5.x) has content for next release (minor or patch). Alpha and beta releases are done from feature branch. Release branch(5.x.y) is created after (last) beta release, near release candidate phase. After branching work for release candidate & final release continues in release branch and feature branch is for next patch release.
Release branch is for finalizing the release. All final releases are done from release branch. Only really important error corrections are allowed to be integrated to release branch. Release team is approving all changes coming in to release branch.
More information about branches from Branch-Guidelines