===Qt Creator Release Cycle===
===Upcoming Releases===
 
Tentative dates:
 
Qt Creator 14


We aim for 3 Qt Creator minor releases each year. Each minor release goes through the following stages before the final release date:
* Feature freeze wk22 (~May 30 2024)
* Beta release wk24 (~Jun 13 2024)
* String freeze wk26 (~Jun 27 26 2024)
* RC release wk28 (~Jul 11 2024)
* Final release wk30 (~Jul 25 2024)


* T-8 Weeks: Feature freeze
Qt Creator 15
* T-6 Weeks: Beta release + soft string freeze
* T-4 Weeks: String freeze
* T-2 Weeks: Release candidate
* T-0 Weeks: Final release


These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.
* Feature freeze wk40 (~Oct 3 2024)
* Beta release wk42 (~Oct 17 2024)
* String freeze wk44 (~Oct 31 2024)
* RC release wk46 (~Nov 14 2024)
* Final release wk48 (~Nov 28 2024)


Patch releases can happen after the final release, mostly with the scope of fixing brown paper bag and high priority issues (see also the [[Submit-Policies|Qt Creator Submit Policies]] ''[qt.io]''). We do not maintain multiple Qt Creator minor releases in parallel, usually there is no patch release after the beta of the next minor release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.
Qt Creator 16


The time after a final (.0) release starts with a period of about two months (52 weeks / 3 releases - 8 weeks from feature freeze to final = 9 1/3 weeks) which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)
* Feature freeze wk5 (~Jan 30 2025)
* Beta release wk7 (~Feb 13 2025)
* String freeze wk9 (~Feb 27 2025)
* RC release wk11 (~Mar 13 2025)
* Final release wk13 (~Mar 27 2025)


===Upcoming Releases===
Qt Creator 17


Tentative dates:
* Feature freeze wk21 (~May 22 2025)
* Beta release wk23 (~Jun 5 2025)
* String freeze wk25 (~Jun 19 2025)
* RC release wk27 (~Jul 3 2025)
* Final release wk29 (~Jul 17 2025)


Qt Creator 4.5
Qt Creator 18


* Feature freeze wk39 (~ Sep 26 2017)
* Feature freeze wk40 (~Oct 2 2025)
* Beta release wk41 (~ Oct 10 2017)
* Beta release wk42 (~Oct 16 2025)
* String freeze wk44 (~ Nov 2 2017)
* String freeze wk44 (~Oct 30 2025)
* Release candidate wk46 (~ Nov 14 2017)
* RC release wk46 (~Nov 13 2025)
* Final release wk48 (~ Nov 28 2017)
* Final release wk48 (~Nov 27 2025)


Qt Creator 4.6
The mentioned dates are typically Thursdays of the weeks, packages are meant to be ready by Tuesday. Actual release then typically happens on Wednesday or Thursday.


* Feature freeze wk03 (~ Jan 16 2018)
A collection of older release plans is found at [[Old Qt Creator Releases]].
* Beta release wk05 (~ Jan 30 2018)
* String freeze wk07 (~ Feb 13 2018)
* Release candidate wk09 (~ Feb 27 2018)
* Final release wk11 (~ Mar 13 2018)


Qt Creator 4.7
===Qt Creator Release Cycle===


* Feature freeze wk20 (~ May 15 2018)
We aim for 3 Qt Creator major releases each year. Each release goes through the following stages before the final release date:
* Beta release wk22 (~ May 29 2018)
* String freeze wk24 (~ Jun 12 2018)
* Release candidate wk26 (~ Jun 26 2018)
* Final release wk28 (~ Jul 10 2018)


Qt Creator 4.8
* T-8 Weeks: Feature freeze
* T-6 Weeks: Beta release + soft string freeze
* T-4 Weeks: String freeze
* T-2 Weeks: Release candidate
* T-0 Weeks: Final release


* Feature freeze wk40 (~ Oct 2 2018)
These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.
* Beta release wk42 (~ Oct 16 2018)
* String freeze wk44 (~ Oct 30 2018)
* Release candidate wk46 (~ Nov 13 2018)
* Final release wk48 (~ Nov 27 2018)


The mentioned dates are typically Tuesdays of the weeks, packages are meant to be ready by then. Actual release typically happens on Wednesday or Thursday.
Patch releases can happen after the final major release, mostly with the scope of fixing embarrassing bugs and high priority issues (see also the [[Submit-Policies|Qt Creator Submit Policies]] ''[qt.io]''). We do not maintain multiple Qt Creator major releases in parallel, usually there is no patch release after the beta of the next release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.


A collection of older release plans is found at [[Old Qt Creator Releases]].
The time after a final (.0) release starts with a period of about two months (52 weeks / 3 releases - 8 weeks from feature freeze to final = 9 1/3 weeks) which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)

Latest revision as of 13:02, 13 June 2024


Upcoming Releases

Tentative dates:

Qt Creator 14

  • Feature freeze wk22 (~May 30 2024)
  • Beta release wk24 (~Jun 13 2024)
  • String freeze wk26 (~Jun 27 26 2024)
  • RC release wk28 (~Jul 11 2024)
  • Final release wk30 (~Jul 25 2024)

Qt Creator 15

  • Feature freeze wk40 (~Oct 3 2024)
  • Beta release wk42 (~Oct 17 2024)
  • String freeze wk44 (~Oct 31 2024)
  • RC release wk46 (~Nov 14 2024)
  • Final release wk48 (~Nov 28 2024)

Qt Creator 16

  • Feature freeze wk5 (~Jan 30 2025)
  • Beta release wk7 (~Feb 13 2025)
  • String freeze wk9 (~Feb 27 2025)
  • RC release wk11 (~Mar 13 2025)
  • Final release wk13 (~Mar 27 2025)

Qt Creator 17

  • Feature freeze wk21 (~May 22 2025)
  • Beta release wk23 (~Jun 5 2025)
  • String freeze wk25 (~Jun 19 2025)
  • RC release wk27 (~Jul 3 2025)
  • Final release wk29 (~Jul 17 2025)

Qt Creator 18

  • Feature freeze wk40 (~Oct 2 2025)
  • Beta release wk42 (~Oct 16 2025)
  • String freeze wk44 (~Oct 30 2025)
  • RC release wk46 (~Nov 13 2025)
  • Final release wk48 (~Nov 27 2025)

The mentioned dates are typically Thursdays of the weeks, packages are meant to be ready by Tuesday. Actual release then typically happens on Wednesday or Thursday.

A collection of older release plans is found at Old Qt Creator Releases.

Qt Creator Release Cycle

We aim for 3 Qt Creator major releases each year. Each release goes through the following stages before the final release date:

  • T-8 Weeks: Feature freeze
  • T-6 Weeks: Beta release + soft string freeze
  • T-4 Weeks: String freeze
  • T-2 Weeks: Release candidate
  • T-0 Weeks: Final release

These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.

Patch releases can happen after the final major release, mostly with the scope of fixing embarrassing bugs and high priority issues (see also the Qt Creator Submit Policies [qt.io]). We do not maintain multiple Qt Creator major releases in parallel, usually there is no patch release after the beta of the next release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.

The time after a final (.0) release starts with a period of about two months (52 weeks / 3 releases - 8 weeks from feature freeze to final = 9 1/3 weeks) which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)