Tentative dates: | Tentative dates: | ||
Qt Creator | Qt Creator 4.0: | ||
* Feature freeze w10 (~Mar 1 2016) | * Feature freeze w10 (~Mar 1 2016) | ||
Line 28: | Line 28: | ||
* Final release w18 (~Apr 26 2016) | * Final release w18 (~Apr 26 2016) | ||
Qt Creator | Qt Creator 4.1: | ||
* Feature freeze w26 (~Jun 21 2016) | * Feature freeze w26 (~Jun 21 2016) | ||
Line 36: | Line 36: | ||
* Final release w34 (~Aug 16 2016) | * Final release w34 (~Aug 16 2016) | ||
Qt Creator | Qt Creator 4.2: | ||
* Feature freeze w44 (~Oct 11 2016) | * Feature freeze w44 (~Oct 11 2016) |
Revision as of 13:35, 24 February 2016
Qt Creator Release Cycle
We aim for 3 Qt Creator minor releases each year. Each minor release goes through the following stages before the final release date:
- T-8 Weeks: Feature freeze
- T-6 Weeks: Beta release + soft string freeze
- T-4 Weeks: String freeze
- T-2 Weeks: Release candidate
- T-0 Weeks: Final release
These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.
Patch releases can happen after the final release, mostly with the scope of fixing brown paper bag and high priority issues (see also the Qt Creator Submit Policies [qt.io]). We do not maintain multiple Qt Creator minor releases in parallel, usually there is no patch release after the beta of the next minor release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.
The schedule for the next minor is typically set around release time, starting with a period about two months which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)
Upcoming Releases
Tentative dates:
Qt Creator 4.0:
- Feature freeze w10 (~Mar 1 2016)
- Beta release w12 (~Mar 15 2016)
- String freeze w14 (~Mar 29 2016)
- Release candidate w16 (~Apr 12 2016)
- Final release w18 (~Apr 26 2016)
Qt Creator 4.1:
- Feature freeze w26 (~Jun 21 2016)
- Beta release w28 (~Jul 5 2016)
- String freeze w30 (~Jul 19 2016)
- Release candidate w32 (~Aug 2 2016)
- Final release w34 (~Aug 16 2016)
Qt Creator 4.2:
- Feature freeze w44 (~Oct 11 2016)
- Beta release w46 (~Oct 25 2016)
- String freeze w48 (~Nov 8 2016)
- Release candidate w50 (~Nov 22 2016)
- Final release w50 (~Dec 6 2016)
The mentioned dates are typically Tuesdays of the weeks, packages are meant to be ready by then. Actual release typically happens on Wednesday or Thursday.