Qt 5.9 Release: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
(Update 5.9.2 schedule) |
||
Line 90: | Line 90: | ||
|5.9.2 | |5.9.2 | ||
|August 2017 | |August 2017 | ||
| | |September 2017 | ||
| | | | ||
|} | |} |
Revision as of 06:06, 31 August 2017
Contact Information
Role | Name | irc | |
---|---|---|---|
Release Manager | Jani Heikkinen | jani.heikkinen@qt.io | jaheikki3 |
Qt 5.9 release plan
Phase | Original plan | Updated plan | Realized |
---|---|---|---|
Soft Branching starts | 25th January 2017 | 26th January 2017 | |
Feature Freeze & Finalize branching | 1st February 2017 | 1st February 2017 | |
Alpha Release | 1st March 2017 | 23rd February 2017 | |
Beta Release | 5th April 2017 | 7th April 2017 | |
Beta2 | 21st April 2017 | ||
API Review | week16/2017 | ||
String freeze | week17/2017 | ||
Beta 3 | 2nd May 2017 | ||
Branch 5.9.0 from 5.9 | week18/2017 | 5th May 2017 | |
Beta4 | 16th May 2017 | ||
Release Candidate | 17th May 2017 | 23rd may 2017 | 23rd may 2017 |
Final Release | 31st May 2017 | 31st May 2017 | |
5.9.1 | June 2017 | 30th June 2017 | |
5.9.2 | August 2017 | September 2017 |
Tools used when building & packaging Qt 5.9
Testing
Qt 5.9 Errors
- Issues to be fixed before Qt 5.9.0
- Issues to be fixed before Qt 5.9.1
- Issues to be fixed before Qt 5.9.2
Qt 5.9 release team meeting memos
- Release team meeting 29.11.2016
- Release team meeting 31.1.2017
- Release team meeting 7.2.2017
- Release team meeting 14.2.2017
- Release team meeting 14.3.2017
- Release team meeting 21.3.2017
- Release team meeting 4.4.2017 ('go' for beta)
- Release team meeting 18.4.2017
- Release team meeting 2.5.2017
- Release team meeting 16.5.2017
- Release team meeting 23.5.2017 ('go' for rc)
- Release team meeting 30.5.2017 ('go' for final)